Project: Tamarack Village Plaza
and Lodge at Osprey Meadows, Tamarack, Idaho
General Contractor: Banner/Sabey,
Seattle, Washington
Description: Remote, destination
resort in a mountainous location in rural Idaho, including:
• |
A 120,000 square foot elevated parking structure |
• |
Six separate 20,000 square foot elevated concrete
buildings |
• |
A 25,000 square foot lodge with three elevated
slabs for parking |
• |
Water feature with waterfall and fountain |
| Scope |
• |
Purchase concrete, pour,
place and finish concrete |
• |
Purchase and place steel reinforcement |
• |
Layout vertical and horizontal form work |
| Project Challenges |
|
• |
Two-year project in remote location required
hiring employees from out of the area and providing housing
for all employees and their families. |
|
• |
Extensive pre-planning was done throughout
the project - due to remote location a two-week lead time
was required for delivery of materials. |
|
• |
Extremely cold weather. Pours were made in
temperatures as cold as 20 degrees below zero Fahrenheit.
1.5 million-BTU heaters and weather covering were used to
maintain adequate temperatures for concrete to cure and to
protect concrete pours from snow. |